Naumkeag

Phase by Phase

The project to restore Naumkeag will take place in five phases over the course of 30 months. Keep track of progress by checking back here.

Naumkeag Blue StepsPhase 1
Through August 2013

  • Infrastructure, Electrical & Water Systems
  • Evergreen Garden Fountain & Sculpture
  • Blue Steps & Runnell
  • Linden Walk
  • Ronde Point
  • South Lawn (incl Oak Lawn & Pagoda)

Afternoon GardenPhase 2
Sept 2013–June 2014

  • Afternoon Garden
  • Peony Terraces

Rose GardenPhase 3
July–December 2014

  • Rose Garden
  • Top Lawn, Perugino View, Great Seat
  • Service Court
  • Greenhouse

Tennis CourtsPhase 4
December 2014–June 2015

  • Top Drive & Waves
  • Plantings below Peony Terrace
  • Chinese Temple Garden
  • Tennis Court & Pavilion

Greenhouses 1950Phase 5
July 2015–July 2016

  • Orchard & Lower Drive
  • Agricultural Fields, Vegetable Terraces & Barns